Timing

Schedule for Stakeholder Input/Meetings, Planning Submittal, Design, NMED Permit Process
(Updated May 31, 2016)

2015

Public Meeting No. 1
Programming
January 20, 2015
Citizens Advisory Committee (CAC) Meeting
Schematic Design Commences
February 17, 2015
North Valley Coalition Meeting February 19, 2015 (evening)
CAC Meeting (3rd Tuesday of the Month) March 17, 2015
Design Advisory Task Force (DATF), formerly
CAC Meeting (3rd Tuesday of the Month)
April 14, 2015
Public Meeting No. 2
Review Site & Building Concepts
April 21, 2015
DATF Meeting (3rd Tuesday of the Month) May 19, 2015
DATF Meeting (3rd Tuesday of the Month) June 16, 2015
Public Meeting No. 3
Present two alternatives
July 15, 2015
Planning (Environmental Planning Commission) Submittal August 27, 2015
Environmental Planning Commission (EPC) Hearing October 8, 2015
EPC Approval October 2015/November 2015
Design Development/Engineering October 2015-January 2016

2016

Withdrawal of request from EPC April 2016
95% Design Development/Engineering Spring 2016 – Late Summer 2016
New Mexico Environment Department (NMED)
Permit Application Submittal
Late Summer 2016-Early Fall 2016
NMED Permit Application Review Fall 2016-Spring 2017
Final Design/Engineering Spring 2017-Summer 2017

 

Note: Schedule subject to change.